Post has attachment
done! project is completed on time and delivered to customer
265 Photos - View album

Post has attachment
To date. Rework of engine coupler. Valves remove for new dcv works

Post has attachment
Up to mount of engine, fabricated coupler for engine. Mount engine after secondary mounts were fabricated and welded to mount plate to create clearance for engine filter.

Post has attachment
Worked on motor mount. We then went to forceAmerica . @ force America we worked on our valves.

Post has attachment
Feb 2 2016. We worked on wheels. We took all the wheels off. Front Wheels are different from back wheels. Steve is helping too order 2 back wheels.
21 Photos - View album

Post has attachment
Friday 1-29-2016. We went to Force America to meet Andrew, who will assist us with the spools we want. We took the valves apart. The spools do not match. Andrew placed order for the spools and also the shaft couplers we went. Andrew will call us midweek, to return on Friday to t assembly and test the repaired valves. Time spent, 8:30 o 11:30
9 Photos - View album

Post has attachment
New engine to replace current to upgrade HP

Post has shared content
Day 1 of final fluid power project

Team member: B, K, E, J
Customer: Ernie P


Upgrade/update of complete system : hydraulics hydrostatic, power steering, seats, prime mover, lights, plumbing, some structural.

Wash, clean, paint.

Tasks done today:
We took picture of the project to start. We also discussed where and what to tackle. We begin by removing seats, floor board and front board to give us better access to the subsystems hidden by these pieces.

We sketched part of the schematics for the steering system on paper. We had Ernie take a look at our progress thus far.

J - 7:00am - 12:00pm
B - 8:00am - 12:00pm
K - 8:00am - 12:00pm
E - 9:00am - 12:00pm
day 1 pix
28 Photos - View album
Wait while more posts are being loaded