Blair station showing some progress.
LRT Construction
LRT Construction
photos.google.com

Post has shared content
Well, next phase is officially on now. With the buses out of the Transitway, work on the LRT outside the tunnels will finally begin.  Work on the Hurdman station has begun some time ago already though, since it will be offset from the current one which can remain in service during construction.

Post has shared content
They have been installing drilled shafts for the LRT's Hurdman Station for the last week. Not continuous flight auger piles though. I guess those will be supporting the elevated rails.



#lightrail #LRT #Ottawa #ConfedreationLine #drilledshafts #piles #boredpiles #construction  
Video
PhotoPhotoPhotoVideo
2014-10-02
5 Photos - View album

Post has attachment
Lees Avenue Rapid Bridge Replacement Time-lapse

Transcript from the site: (http://www.confederationline.ca/en/)

--------------------------
Beginning the evening of Saturday, September 6 and continuing into the early morning of Sunday, September 7, the new Lees Avenue overpass was moved into place using Rapid Bridge Replacement construction techniques.

At 2,100 tonnes, the new bridge is the heaviest rapid replacement structure over a highway in North America. It is also the 6th of its kind to be installed in the Ottawa area.

We collected thousands of still photos from the installation and created a time lapse video to show you how it all came together.

Following 10 months of off site construction on the bridge itself, a team of approximately 100 people completed the final process of installation in less than 18 hours.The newly improved Lees Avenue Bridge will reopen for public use during the week of Septemb er 15, 2014. The full Lees Avenue roadway will be reopened in late fall.
--------------------------

#transcript #video #timelapse #Ottawa #LRT #ConfederationLine #Construction #LightRail

Post has attachment
Construction Summary for the week of September 7


#Construction #Ottawa #LRT #LightRail #ConfederationLine
Construction Summary
Construction Summary
confederationline.ca

Post has attachment
Status of the tunnel construction as of the week of September 7 2014.


#Construction #Ottawa #LRT #LightRail #ConfederationLine
 #Tunnel #Roadheader
Roadheaders
Roadheaders
confederationline.ca

Post has attachment

Post has attachment
Last week prep work has begun for the Hurdman Station.  The workers are replacing pipes along the future rail path. The upcoming Hurdman station will be constructed about the same location.

Next Saturday, the bridge replacement at Lees will take place.
Photo

Post has attachment
Rapid bridge replacement coming up. September 6. Bring your camera, comfy chair, and time to spare. Highway closure starts at 18:00 and there will be some public viewing area in the parking lot of the LEES campus at the University of Ottawa.




#Ottawa #LRT #Bridgereplacement #Bridge_Replacement #LigtRail #Light_Rail #Construction #News #Ontario #Canada #PublicTransit #Public_Transit #Train

Post has attachment
This is a community to share news of the developments surrounding the light rail project under construction in Ottawa.

You are welcome to share any bit of information regarding this project.


#LRT #Confederationline #construction