LIVE FROM CONSTRUCTION SITES - KSA - RIYADH
The FAST consortium is living up to its name, with rapid progress on Lines 4, 5 and 6 of the Riyadh Metro.
The consortium is designing and constructing the three lines, which involve extensive elevated sections.
DEAL is involved in the project as a provider of engineering services, as a supplier of equipment (2 gantry cranes, 14 moulds, post tensioning equipment and materials, 3 launching girders for span-by-span erection) and through the presence of supervisors and DEAL employees on site for the prefabrication and the launching of segments.

DEAL's launchig equipment is capable of minimizing the impact of work zones on traffic and manage alignment of elevated metro lines in urban areas on very tight horizontal radius.
PhotoPhotoPhotoPhoto
26/01/17
4 Photos - View album

Post has attachment
Public
CASE STUDY - EGYPT - EL AIN SOKHNA

The innovative solution designed, manufactured and supplied by DEAL for the construction of this supercritical power plant in Egypt, consists of a steel frame supporting a 36m long pipe that can be positioned with particular precision inside the previously excavated trench.

A system of hydraulic jacks, managed by a control station on barge and hydraulically powered by an umbilical pipe on reel, allows the very accurate positioning and the connection with the previously laid sections.

This equipment drastically reduces underwater pipe laying and installation activities that would otherwise be carried out with crawler cranes positioned on barges, guided by a crew of divers working in a very low visibility environment.

www.deal.it
PhotoPhotoPhoto
17/01/17
3 Photos - View album

Post has attachment
Public
READY FOR A NEW CHALLENGE - DENMARK - ROSKILDE FJORD LINK

The project includes the design and construction of an 8km-long dual-carriageway highway, comprehensive of a 1.4-km-long bridge over the Roskilde Fjord, as well as several smaller civil structures and 1 km of approach roads.

The aim is to replace the old bridge built in 1935 and reduce serious traffic congestion by providing an alternative to the only currently active bridge over the fjord.

DEAL is supplying: 3 moulds, 2 second-hand straddle carriers, 1 manipulator for segment shifting on barge, 1 second-hand launching girder, as well as the following engineering services: geometry control, precast yard design, temporary works, manuals and sequences for Roskilde Bridge.

www.deal.it
Photo

Post has attachment
Condividiamo con voi qualche foto pre e post-corsa dei valorosi corridori DEAL BRIDGE RUNNERS 2016!
Complimenti a tutti e un enorme ringraziamento per la passione, lo spirito di squadra, il tifo e i tanti km di beneficienza donati a Telethon per sostenere la ricerca scientifica contro le malattie genetiche rare!

We'd like to share with you some pictures of DEAL BRIDGE RUNNERS 2016!
Congratulations to everyone and a big thanks for your dedication, team spirit, support and all the kilometres given to Telethon foundation, a leading Italian charity organization investing in the research on rare genetic diseases!
PhotoPhotoPhotoPhotoPhoto
05/12/16
9 Photos - View album

Post has attachment
LIVE FROM CONSTRUCTION SITES - France - Rennes metro viaduct - Line B

Erection activities are being carried out successfully! 
The first double span has been erected and we are currently  working on the second one. 

At this stage, DEAL is deeply involved on site activities.  Our technical team, based on site,  is monitoring and supervising the erection operations as  every single phase needs to meet specific technical requirements.

www.deal.it
PhotoPhotoPhotoPhoto
30/11/16
4 Photos - View album

Post has attachment
Thanks to everyone who stopped by our booth at Congreso Nacional de la Infraestructura in Cartagena de Indias (Colombia) last week.
Photo
Photo
27/11/16
2 Photos - View album

Post has attachment
LIVE FROM CONSTRUCTION SITES - Qatar - Doha - Red Line North

DEAL SETS A NEW RECORD!
CONSTRUCTION OF A 52-METERS SPAN WITH U-SHAPED SECTION AND USING SPAN BY SPAN METHOD.

DEAL has recently completed erection of a 4-span continuous deck unit composed of 4 spans having length 34+52+52+30m.
In order to erect this unit, DEAL has pushed to the limits the span by span methodology along with the relevant erection equipment to reach this goal for the first time ever in this kind of structures.
Compared to the traditional methods (i.e. balanced cantilever), cost benefits have been achieved by the innovative solution too.
PhotoPhotoPhotoPhoto
18/11/16
4 Photos - View album

Post has attachment
Save the dates!
Photo

Post has attachment
Live pictures of DEAL and TENSA booth at ASBI – American Segmental Bridge Institute - 28th Annual Convention in Long Beach, CA.
PhotoPhotoPhoto
09/11/16
3 Photos - View album

Post has attachment
It is with the greatest pleasure that we present our newly redesigned website.

Contents have been updated and improved to more closely reflect our activities and focus, our services and references are presented in much more detail (the projects page is still in progress) and the news page is linked to our online activity on social media.

The website is also optimized for mobile devices like smartphones or tablets. Enjoy, and please tell us what you think!

www.deal.it
Photo
Wait while more posts are being loaded